Draft approach 3: Technology-Led

Closed8 Mar, 2021, 12:00am - 14 Jun, 2021, 11:59pm

Technology-Led

Try new ways to move clean energy across the country

One of the challenges of clean electricity is how to move large amounts of power from source to use. Rather than put generation near demand, or demand near generation, this approach considers innovative ways to move the power itself.

The purpose of the grid is to move power in bulk over long distances, while also integrating this power throughout the entire network. Achieving these goals typically requires overhead lines carrying alternating current (AC) – as they are reliable and robust. But, as noted in Approach 2, it would be very challenging to complete the required amount of new AC lines before 2030.

As an alternative, this approach uses a high-capacity underground direct-current (DC) cable. This cable would exclusively move power from wind and solar farms in the North and West to the greater Belfast area where more power is needed.

High-voltage DC cables like this are typically used in long-distance connections between separate grids. They are rarely used as an integrated part of any national electricity grid. This is because DC electricity is hard to integrate with existing AC grid infrastructure. For instance, DC cables like this need large, expensive and complex converter stations at both ends of every cable.

For these reasons, these DC cables would not form an integrated part of the grid. They would be isolated, one-way connections between renewable generation and urban centres.

To enable this approach, we will also need to install sophisticated electronic devices on existing AC lines – to change how power flows on the rest of the grid.

Although SONI plans for the future of the grid, NIE Networks builds and owns the actual grid infrastructure. To deliver this approach, we would need to work together to implement these technologies at an unprecedented scale.

What work will be needed, and how much might it cost?

This draft approach is based on 700 MW of new renewable generation coming from inland wind farms and 350 MW each from solar and offshore wind.

We estimate it would lead to over 14 projects costing approximately £535 million to upgrade and add to the grid. There is also a high degree of technical uncertainty in this draft approach.

For this reason, we believe it would be very challenging to complete all the necessary work in time. This means this approach is unlikely to make the grid ready for at least 70% clean electricity by 2030.

EirGrid - Shaping Summary - Cropped Approach Images1

What might this draft approach look like?

This approach uses a high-voltage DC underground electricity cable to move power from the north and west to the east. This cable would need large-scale converter stations at either end so power can reconnect to the grid. Converter stations are substantial buildings, but their visual impact can be reduced with careful landscaping.

Mao of Northern Ireland with Approach 3 illustrated

Draft Approach 3: Technology-Led
All infrastructure should go underground. It should be paid for by the datacentres which are set to use 70% of power. Communities should have the first say on what happens in their areas. Eirgrid...
Draft Approach 3: Technology-Led
We both agree and disagree with this statement. A transmission and distribution network will be required in any case; power must be moved from generation to demand centre, and HVCD can help in...
Draft Approach 3: Technology-Led
Slightly disagree. While the Council acknowledges the issues of integrating HVDC with HVAC grid systems, it considers that this mode of transmission is likely to become more prevalent in future...
Draft Approach 3: Technology-Led
-
Draft Approach 3: Technology-led
There are many risks to this approach and it seems unlikely to be able to fulfil NI's energy goals. As per other points in this responses, any new approaches have to be underpinned by...